CURRENT PROJECT STATUS:
UCONN 2000 - PHASE III
|
April 2005 | |||||||
|
(UCONN 2000 general funding for Phase III only; does
not include previous funding or other funding sources.)
|
||||||||
|
||||||||
|
Project Description
|
UCONN 2000 Funding*
|
Comments
|
IMPLEMENTATION
Planning/Design
|
Completed to date
25% 50% 75% 100% |
||||
Arjona & Monteith (new classroom building) |
$66,100,000
|
Preliminary planning complete negotiate design contract. | *** | |||||
CLAC Renovation Biosafety Level 3 Lab - Health Center |
$14,000,000
|
Study complete. | ****** | |||||
Deferred Maintenance/Code/ADA Renovation Lumpsum |
$17,360,000
|
FY '05 Projects are in the works. | ||||||
Deferred Maintenance/Code/ADA Renovation Lumpsum - Health Center: FY05 |
$2,850,000
|
FY '05 Projects are in the works. | ********* | |||||
| Dental School Renovation - Health Center |
$5,000,000
|
Pre-design work complete. | ****** | |||||
| Equipment, Library Collections & Telecommunications - Health Center |
$7,900,000
|
FY '05 acquisitions underway. | ****** | |||||
Farm Building Repairs & Renovations |
$6,000,000
|
Poultry Consolidation Unit complete. Yellow Barn stabilization in progress. | **************** |
|
||||
Intramural, Recreational & Intercollegiate Facilities |
$31,000,000
|
Construction started.. | ********************************* |
|
||||
Lakeside Renovations |
$3,800,000
|
Design development underway. | ***** | |||||
Law School Renovations & Improvements |
$15,000,000 | Final design. | ****************************** | |||||
Library/Student Center Renovation - Health Center |
$5,000,000
|
FY '05 funds $150,000 for abatement of hazardous materials. Work completed. | ***** | |||||
| Main Building Renovations - Health Center |
$75,000,000
|
Project planned to begin in May. '05 | ||||||
Medical School Academic Building Renovation - Health Center |
$9,000,000
|
Architect selected for auditoria renovations. | *** | |||||
Natural History Museum Completion |
$3,900,000
|
Schematic Design | ******* | |||||
North Hillside Road Completion |
$7,500,000
|
Wetland permits under review. | ********** | |||||
Research Tower - Health Center |
$60,000,000
|
Architect/Engineers selected. | *** | |||||
Residential Life Facilities |
$60,000,000
|
FY '05 piece complete. | ********************************** |
|
||||
Torrey Renovation Completion & Biology Expansion |
$65,000,000
|
Preliminary planning on hold. | *** | |||||
West Hartford Campus Renovations & Improvements |
$25,000,000 | Parking Lot Repairs out to bid. | ***************************** | |||||
| * UCONN 2000 general funding for Phase III only;
does not include previous funding or other funding sources.
|
||||||||