Return to Report #20

CURRENT PROJECT STATUS: UCONN 2000 - PHASE III
April 2005
(UCONN 2000 general funding for Phase III only; does not include previous funding or other funding sources.)
CHART KEY: *** = Planning and Design Completed
= Construction Completed
Project Description
UCONN 2000 Funding*
Comments
IMPLEMENTATION
Planning/Design
Completed to date
25% 50% 75% 100%

Arjona & Monteith (new classroom building)

$66,100,000
Preliminary planning complete negotiate design contract. ***  

CLAC Renovation Biosafety Level 3 Lab - Health Center

$14,000,000
Study complete. ******  

Deferred Maintenance/Code/ADA Renovation Lumpsum

$17,360,000
FY '05 Projects are in the works.    

Deferred Maintenance/Code/ADA Renovation Lumpsum - Health Center: FY05

$2,850,000
FY '05 Projects are in the works. *********  
Dental School Renovation - Health Center

$5,000,000
Pre-design work complete. ******  
Equipment, Library Collections & Telecommunications - Health Center

$7,900,000
FY '05 acquisitions underway. ******  

Farm Building Repairs & Renovations

$6,000,000
Poultry Consolidation Unit complete. Yellow Barn stabilization in progress. ****************

Intramural, Recreational & Intercollegiate Facilities

$31,000,000
Construction started.. *********************************

Lakeside Renovations

$3,800,000
Design development underway. *****  

Law School Renovations & Improvements
$15,000,000 Final design. ******************************  

Library/Student Center Renovation - Health Center

$5,000,000
FY '05 funds $150,000 for abatement of hazardous materials. Work completed. *****  
Main Building Renovations - Health Center

$75,000,000
Project planned to begin in May. '05    

Medical School Academic Building Renovation - Health Center

$9,000,000
Architect selected for auditoria renovations. ***   

Natural History Museum Completion

$3,900,000
Schematic Design *******  

North Hillside Road Completion

$7,500,000
Wetland permits under review. **********  

Research Tower - Health Center

$60,000,000
Architect/Engineers selected. ***  

Residential Life Facilities

$60,000,000
FY '05 piece complete. **********************************

Torrey Renovation Completion & Biology Expansion

$65,000,000
Preliminary planning on hold. ***  

West Hartford Campus Renovations & Improvements
$25,000,000 Parking Lot Repairs out to bid. *****************************  
* UCONN 2000 general funding for Phase III only; does not include previous funding or other funding sources.
 

Return to UCONN 2000 UPDATE #20.