CURRENT PROJECT STATUS: UCONN 2000 - PHASE
II
|
April 2005 | |||||||
|
(UCONN 2000 general funding for Phase II only; does not
include previous funding or other funding sources.)
|
||||||||
|
||||||||
|
Project Description
|
UCONN 2000 Funding*
|
Comments
|
IMPLEMENTATION
Planning/Design
|
Completed to date
25% 50% 75% 100% |
||||
Agricultural Biotechnology Facility Completion |
$3,000,000
|
Phase II Construction complete. | ********************************** |
|
||||
Alumni Quad Renovations |
$11,500,000
|
Construction complete. | ********************************** |
|
||||
Avery Point Marine Sciences Research Center |
$7,341,000
|
Construction complete. | ********************************** |
|
||||
Avery Point Undergraduate Building Renovations |
$5,323,000
|
Design and construction underway for various projects. | *********************** |
|
||||
Beach Hall Renovations |
$0
|
Project cancelled. | ||||||
Central Warehouse New |
$6,933,752 | Construction complete | ********************************** |
|
||||
Deferred Maintenance Lump Sum |
$118,8675,954
|
Bidding and awarding contracts for FY 03-05 projects. On-going work. | ||||||
East Campus North Renovations |
$7,710,000
|
Construction complete. | ********************************** |
|
||||
Equipment, Library Collections and Telecommunications |
$105,812,000
|
Equipment and Library collections have been ordered for FY03-05. | ||||||
Gant Plaza |
$3,013,294
|
Construction complete. | ********************************** |
|
||||
Gentry Renovations |
$10,000,000
|
Construction underway. | ********************************** |
|
||||
Grad Dorm Renovations |
$3,000,000
|
Construction complete. | ********************************** | |||||
Hilltop Dorm Renovations |
$8,700,000
|
Construction complete. | ********************************** |
|
||||
Hilltop Dormitory - New |
$0
|
Construction complete. | ********************************** |
|
||||
Hilltop Student Apartments |
$0
|
Construction complete. | ********************************** |
|
||||
Horticulture, Convert to Natural History Museum |
$800,000
|
Construction complete. | ********************************** |
|
||||
Manchester and DRM Renovations |
$0
|
Project cancelled. | ||||||
Mansfield Training School Improvements |
$3,500,000
|
Construction complete. | ********************************** |
|
||||
Monteith Renovations |
$733,000
|
Project withdrawn. | ||||||
Music Drama Addition |
$7,400,000 | Construction complete. | ********************************** |
|
||||
North Campus Renovations |
$11,866,000
|
Construction complete. | ********************************** |
|
||||
North Campus Apartments |
$0
|
Construction underway. | ********************************** |
|
||||
Northwest Quadrant Renovations |
$30,000,000
|
Construction complete. | ********************************** |
|
||||
Pharmacy - New Building |
$84,753,000
|
Construction started. | ********************************** | |||||
School of Business - New Building |
$5,000,000
|
Construction complete. | ********************************** |
|
||||
School of Business Renovations |
$8,000,000
|
Construction underway. | ********************************** |
|
||||
Shippee/Buckley Renovations |
$7,000,000
|
Construction complete. | ********************************** |
|
||||
South Parking Garage |
$0
|
Construction complete. | ********************************** |
|
||||
Student Union Addition |
$39,820,000
|
Construction underway. | ********************************** |
|
||||
Tech Quad: Phase I-A: Biological Sciences I |
$2,090,000
|
Construction complete. | ********************************** |
|
||||
Tech Quad: Phase II: |
$34,120,000
|
Construction complete. | ********************************** |
|
||||
Torrey Life Sciences Renovations |
$2,181,000
|
In design/temporarily on hold. | ***** | |||||
Towers Dining Hall |
$500,000
|
Construction complete. | ********************************* |
|
||||
Towers Greek Housing |
$0
|
Construction complete. | ********************************* |
|
||||
Towers Interior Renovations |
$19,500,000
|
Construction complete. | ********************************* |
|
||||
Underground Steam and Water Upgrade |
$6,000,000
|
Construction complete. | ********************************** |
|
||||
Waring Building - Convert to Classrooms |
$10,536,000
|
Construction complete. | ********************************** |
|
||||
Waterbury Downtown Campus |
$0
|
Construction complete. | ********************************** |
|
||||
West Campus Renovations |
$500,000
|
Construction complete. | ********************************* |
|
||||
Wilbur Cross Renovations |
$14,000,000
|
Construction complete. | ********************************** |
|
||||
| * UCONN 2000 general funding for Phase II only;
does not include previous funding or other funding sources.
|
||||||||