CURRENT PROJECT STATUS: UCONN 2000 - PHASE I April 2005
(UCONN 2000 funding only; does not include previous funding or other funding sources.)
CHART KEY: *** = Planning and Design Completed
= Construction Completed
Project Description
UCONN 2000 Funding*
Comments
IMPLEMENTATION
Planning/Design
Construction
Completed to date
25% 50% 75% 100%

Agriculture Biotechnology
Facility:

$9,400,000
Phase I construction complete *********************************

Avery Pt. Marine Science &
Technology Center: Phase 1

$30,000,000
Construction complete. *********************************

Babbidge Library Envelope
Repairs

$0
Construction complete. *********************************

Benton State Art Museum Addition

$700,000
Construction complete. *********************************

Chemistry - New Building

$53,062,000
Construction complete. *********************************

Deferred Maintenance and Renovation Lump Sum

$40,792,000
Phase I construction complete. *********************************

Equipment, Library Collections & Telecommunications

$ 60,500,000
Phase I complete. *********************************

Fairfield Road Pedestrian Mall

$6,074,000
Construction complete. *********************************

Gant Plaza

$3,516,000
Construction complete. *********************************

Hartford Relocation Feasibility Study

$0
Project cancelled.  
 

Heating Plant Upgrade

$9,969,000
Construction complete. **********************************

Ice Rink Enclosure

$3,280,000
Construction complete. **********************************

Litchfield Agricultural Center

$1,000,000
Construction complete. **********************************

Mansfield Apartments Renovations

$2,071,000
Construction complete. **********************************

North Superblock Site & Utilities

$7,668,000
Construction complete. **********************************

Northwest Quadrant Renovation

$2,001,000
Construction complete. **********************************

Parking Garage - North

$9,658,000
Construction complete. **********************************

Pharmacy - New Building Phase I

$3,856,000
Construction uderway. **********************************

School of Business - New Building

$19,559,000
Construction complete. **********************************

South Campus Dorms & Dining Hall

$12,251,000
Construction complete. **********************************

Stamford - Relocation to Downtown

$55,785,000
Construction complete. **********************************

Tech Quad: Phase I-A: Biological Sciences I

$37,903,000
Construction complete. **********************************

Underground Steam & Water Upgrade: Phase I

$6,000,000 Construction Complete **********************************

University Programs New Building

$0
Construction complete. Funded through UCONN Foundation. **********************************

Waring Building Conversion

$916,000
Construction complete. **********************************

Waterbury Property Purchase

$200,000
Property purchased in January, 1999.


White Building Code Violation Abatements

$2,430,000
Construction complete. **********************************

Wilbur Cross Building Renovations

$3,409,000
Construction complete. **********************************
* UCONN 2000 general funding only; does not include previous funding or other funding sources.