|
UCONN 2000
Legislative Update No. 12
April 2001
REBUILDING, RENEWING AND ENHANCING
THE UNIVERSITY OF CONNECTICUT
The TWELFTH in a series of reports
to Governor John G. Rowland and the Connecticut
General Assembly
This is the twelfth in a series of semi-annual reports to the Governor and the
General Assembly pursuant to the provisions of Sections 10a-109 through 10a-109y
of the Connecticut General Statutes, originally An Act to Enhance the Infrastructure
of the University of Connecticut, now known as UCONN 2000. These reports have been
issued each October and April since passage of UCONN 2000 on June 7, 1995. The
law also required a four-year progress report, which was filed on January 15, 1999.
The structure of the previous reports is utilized in this report.
There are many tangible indicators of success of the UCONN 2000 Program: new
and renovated facilities, state-of-the-art equipment, growing enrollment, enhanced
faculty recruitment, and increased funding via sponsored research and major donations.
These all breed investor confidence in the University, as respect among those in
the financial markets continues to grow.
Moody's Investors Services upgraded the University's General Obligation Bonds
secured by the State's Debt Service Commitment to "Aa2" from "Aa3" in
February. The strong link between the State's and University's credit ratings was
shown by the simultaneous equivalent upgrade of the State's General Obligation
Bonds. Underscoring the University's and State's perceived linkage by financial
markets, the UCONN 2000 Student Fee Revenue Bonds Series 1998-A were upgraded to "Aa3" from "A1." These
upgrades represent the market's recognition of the University and its UCONN 2000
program as a sound investment.
UCONN 2000: ACTIVITIES COMPLETED OR UNDERWAY
The Board of Trustees at its November 9, 2000 meeting approved a revised FY
2000-01 Capital Budget. The projects included and their budgets are listed below:
| Projects |
Amount Approved
April 11, 2000 |
Proposed Revised
Capital Budget |
| Beach Hall Renovation |
$ 500,000 |
$ 0 |
| Deferred Maintenance Renovation Lumpsum GF |
20,000,000 |
22,300,000 |
| Equipment Replacement/Upgrade |
20,000,000 |
20,000,000 |
| Gant Plaza |
0 |
3,000,000 |
| Gentry Renovations |
500,000 |
1,000,000 |
| Hilltop Dorm Improvements |
700,000 |
700,000 |
| Mansfield Training School |
1,500,000 |
1,500,000 |
| Monteith Renovations |
5,300,000 |
0 |
| North Campus Renovations |
5,000,000 |
5,000,000 |
| School of Business (New) |
0 |
3,000,000 |
| School of Business-Renovation |
12,000,000 |
12,000,000 |
| School of Pharmacy/Biology |
29,000,000 |
23,000,000 |
| Student Union Addition |
5,000,000 |
5,000,000 |
| Towers Renovation |
500,000 |
500,000 |
| Wilbur Cross Renovation |
0 |
3,000,000 |
| Total |
$100,000,000 |
$100,000,000 |
At the February 22, 2001 Board of Trustees meeting, an accelerated plan for
completion of fire safety renovations in campus residence halls was approved; specifically,
insuring that sprinklers would be installed and operational for 95% of all beds
by the start of the Fall 2003 semester in accordance with the following schedule.
| Complex |
Number of
Buildings |
Completion
Schedule |
Number
of Beds |
Cumulative %
of All Beds |
| South Campus |
4 |
Complete |
674 |
5.91% |
| Northwest Quad |
7 |
Complete |
1,004 |
14.71% |
| North Campus |
11 |
Complete |
1,326 |
26.34% |
| McMahon Hall |
3 |
August 2001 |
574 |
31.37% |
| Hilltop Dorms |
3 |
August 2001 |
560 |
36.29% |
| Hilltop Apartments |
- |
August 2001 |
968 |
44.77% |
| New Hilltop Dorms-Phase I |
- |
August 2001 |
248 |
46.95% |
| New Hilltop Dorms-Phase II |
- |
January 2002 |
202 |
48.72% |
| Towers |
6 |
August 2002 |
988 |
57.38% |
| ALumni Quad |
5 |
August 2002 |
836 |
64.71% |
| North Campus Apartments |
- |
August 2002 |
1,000 |
73.48% |
| Buckley/Shippee |
4 |
August 2003 |
707 |
79.68% |
| Grad Dorms |
8 |
August 2003 |
440 |
83.54% |
| Graduate Apartments |
- |
August 2003 |
1,000 |
92.31% |
| Greek Housing |
- |
August 2003 |
300 |
94.94% |
| Holcomb/Whitney/Sprague |
3 |
August 2004 |
372 |
98.20% |
| Hicks/Grange |
2 |
August 2004 |
205 |
100.00% |
| Total |
|
|
11,404 |
|
|
Note: Preliminary plans call for the existing West Campus dorms to be
demolished in 2004 and replaced in the future.
|
By Fall 2000, smoke detectors, automatic door closers and addressable alarms
had been installed in all residence halls.
At its February 22, 2001 meeting the Board of Trustees accepted the final draft
of the University of Connecticut Outlying Parcels Master Plan including the Agricultural
Area, North Campus and the Depot Campus. The Master Plan identifies opportunities
for potential future development in these outlying parcels and completes the long-range
planning for all of the University's significant holdings at the main campus.
The Board of Trustees at its April 12, 2001 meeting approved the FY 2001-02
Capital Budget. The projects included and their budgets are listed below:
| Project |
Budget |
| Deferred Maintenance, Renovation Lumpsum-GF |
$27,000,000 |
| Equipment Replacement/Upgrade |
18,000,000 |
| Hilltop Dorm Renovations |
8,000,000 |
| Student Union Addition |
10,000,000 |
| Gentry Renovations |
7,000,000 |
| Mansfield Training School Improvements |
2,000,000 |
| School of Pharmacy/Biology Building |
9,000,000 |
| Agricultural Biotechnology Facility Completion |
3,000,000 |
| Technology Quadrant Phase II (Engineering) |
16,000,000 |
| Total |
$100,000,000 |
The Board also approved the Seventh Supplemental Indenture that covered these
general obligation projects.
The University is proceeding with completion of the Agricultural Biotechnology
Facility.
A Department of Energy Grant ($7,770,682) along with $3,000,000 from UCONN 2000
will provide funding for the second phase of the project. The University has already
occupied the completed first building. The project includes construction of a second
building (approx. 16,000 sq. ft.) and a new greenhouse facility (approximately
14,000 sq. ft.) as provided in the original project and the Master Plan. The facility
will provide for research and incubation space. Architects for the project are
Svigals Associates of New Haven and the construction manager is Turner Construction
of Milford. Construction will begin in May and be completed in March 2002.
The Environmental Impact Evaluation is being completed for the North Campus.
The primary land uses for the North Campus will be University-related research,
technology/research, student residential housing, remote parking, and special academic
and support services. The North Campus parcel occupies the same approximate boundaries
as the formerly proposed Technology Park.
Developers have been selected for the student residential housing to be located
in the southernmost portion of North Campus (immediately adjacent to the Northwest
Quad complex). The project to be developed at this site will be for 1,000 beds
of apartment style housing. A land lease agreement will be signed with the developer
who will be responsible for obtaining his financing. At the completion of the construction,
the developer will own and manage the buildings and manage the leasing of the apartments.
The developer selected is JPI of Irving, Texas. They have developed over 20,000
beds of apartment style housing at other universities under similar arrangements.
The firm of Wank Adams Slavin Associates of New York City is finalizing designs
for installation of sprinklers in the Hilltop Dorms and McMahon Hall. Along with
this work will be other fire code repairs, roof and faìade repairs, asbestos
abatement and interior improvements. The construction manager for the project is
Whiting-Turner of New Haven. This project will be completed over the summer so
the buildings will be ready for the Fall 2001 semester.
Schematic Design activities have been completed for renovations at the School
of Law that will provide for the phased renovations of facilities including the
old Library Building. The architect for this project is Allan Dehar Associates
of New Haven.
Design Development activities are underway for renovations to the current School
of Business building. The purpose of this project is to turn the old facility into
a new Learning Center that will provide academic support for students as well as
instructional support for faculty members and graduate students. Functions included
in the facility will be the First Year Experience program (special seminars and
activities for incoming freshmen), Career Services, Institute for Teaching & Learning,
Study Abroad, Urban Semester, Center for Community Outreach, Instructional Research
Center, Honors Program, and Learning Research Center. The architect for the project
is Svigals Associates of New Haven.
Construction documents are being prepared for the Student Union project, which
will include major renovations and additions to the current facility. The primary
goal is to expand the range and quality of activities available to students in
the campus core. Included in the project will be a food court, 500-seat theatre,
meeting space, a ballroom and a central post office for all student mail. This
facility also will provide new space for each of the campus' cultural centers.
Implementation of the project will be phased over several years. The architects
for the project are Cannon Associates of Boston. Konover Construction of West Hartford
has been selected as construction manager for the project.
As part of the overall building and renovation program, the University of Connecticut
continues the process of standardizing building systems and system components (such
as electrical circuitry, panel boxes, etc.). This standardization process will
reduce the number of replacement parts the University needs to inventory, speed
repairs, improve the level of maintenance and lower overall costs.
Design development drawings are under review for the new School of Pharmacy/Biology
building. The project involves the construction of a 120,000 square foot building
for teaching and research for Pharmacy and the creation of a 55,000 square foot
building of research space for Biology. The architect for the project is Davis,
Brody Bond of New York City. Gilbane of Glastonbury was selected as construction
manager for the project.
Construction documents are being prepared for the Technology Quad Phase II project.
This project involves the construction of a new building for the School of Engineering's
Information Technology program. This facility, projected to be approximately 94,000
gross square feet, will include offices, classrooms, research labs, and a 350-seat
lecture hall. The architect for the project is Burt Hill Kosar Rittlemann of Washington,
D.C. O&G Construction of Torrington was selected as construction manager for
the project.
Preparation of design documents for renovations to the Neag School of Education's
Gentry building are underway. The project scope includes a complete renovation
of the building's interior along with exterior improvements of the faìade
and roof, and an addition to the building. Architects for the project are Svigals
Associates of New Haven. UCONN 2000 funds for the project will be augmented by
private fundraising.
Design activities are underway for an addition to the Benton Museum. This $1,500,000
project is funded through a combination of UCONN 2000 funds ($700,000) and private
gifts. Architects for the project are Gregg & Weiss of New Haven.
Design development activities are underway for the Waterbury Downtown campus
project, funded by State General Obligation bonds. The project will involve relocation
of the Waterbury Regional campus from its present Hillside location to East Main
Street. The existing academic programs, along with additional Bachelor of Business
and MBA programs, will be offered in the new facilities. The architect for the
project is Jeter Cook & Jepson of Hartford. Although not part of UCONN 2000
funding, new legislation provides that the project will be managed by the University
with the authority set forth in UCONN 2000. O&G Construction of Torrington
was selected as construction manager for the project.
The Architectural and Engineering Services Home Page on the World Wide Web continues
to be very successful in providing information to interested parties. The site
has been visited almost 25,000 times since its introduction in October 1996.
- Construction activities are almost complete for the Waring Building renovation,
which creates additional classrooms and offices for the College of Liberal Arts
and Sciences and the English and Geography Departments. The building will be occupied
in June 2001. The contractor for the project is Hayes Construction of Seymour.
- Installation of new exterior signage is underway on the main campus, Health
Center, law school and regional campuses. The purpose of the program is to incorporate
signage that will provide a unified look and better directional information to
visitors at all University campuses.
- Construction activity is continuing on the Avery Point Marine Sciences project.
This project includes a new 116,000 square foot research building, a 30,000 square
foot Project Oceanology building, and a new central chilled water plant. The Project
Oceanology building was occupied in June 2000. The Marine Sciences Center was completed
in February 2001. The contractor on the project is C.R. Klewin of Norwich. Demolition
of old buildings and other site activities remain to be completed.
- Construction is complete on the Litchfield Agricultural Center project. The
contractor for the project is Hayes Construction of Shelton. Funding for the project
included UCONN 2000 funds and a grant from the Litchfield Agricultural Center.
- Construction is underway for the complete renovation of the Wilbur Cross building.
This project will provide an opportunity to locate all business functions related
to student services in one central, customer-friendly location. These functions
include dining services, residential life, financial aid, bursar, registrar, and
services to students with disabilities. The contractor for the project is Aspinet
Construction of Avon. Construction activities will be completed in two phases,
with the first phase completion scheduled for June 2001. The remainder of the project
will be completed in March 2002.
- Construction is complete on renovations to the Horticultural Storage building,
which is the new location of the Natural History Museum. The museum is undertaking
fund raising activities to supplement UCONN 2000 funds.
- Construction activities are underway for the Gant Plaza Deck repair project.
The project will include the construction of a 14,000 square foot building on the
deck for the Institute of Materials Science and installation of a new deck waterproofing
system. The construction manager for the project is Whiting-Turner of New Haven.
The project is scheduled for completion in June 2001.
- Construction is underway on a hotel located on the Storrs campus being constructed
under a land-lease agreement with the University. The hotel is being built next
to the Lewis B. Rome Commons building at South Campus to take advantage of its
conferencing and catering capacity in conjunction with the hotel. The partnership
for the project is Robert Freidman (hotel developer and owner of the Norwich Navigators)
along with the Maristar Group, which manages hotels worldwide, including many university
hotel facilities such as the Princeton Forestal. It is anticipated that the construction
will be complete in September 2001. The contractor for the project is G. Schnip
Construction of Norwich.
- Construction is underway for the second parking garage, to be located next to
the Gampel Pavilion. The cost of the project is borne by a special obligation bond
issued under UCONN 2000 authority. The revenue to support the debt service will
come from parking and transportation fees. The facility will contain 1,547 parking
spaces and 53,000 gross square feet of retail space for the UConn Co-op. The garage
will be completed in May 2001 and the Co-op space in October 2001. The contractor
for the project is Manafort Brothers of New Britain.
- The construction of additional dormitories at the Hilltop complex is underway.
The project will create 450 beds for students in suite style rooms. Financing for
the project is secured by special revenue bonds to be repaid through room and board
fees. With enrollments increasing, these additional beds will help avoid overcrowding.
The project schedule will have 248 beds ready in August 2001 with the remaining
202 beds available in January 2002. Konover Construction of West Hartford is the
contractor for the project.
- Construction is underway for the Hilltop Student Apartments. This project will
accommodate 972 students. Part of the Hilltop residential neighborhood, the project
is on Alumni Drive, immediately south of the Hilltop Dorms. The apartments will
be rented to University students only; tenants will be subject to the University's
code of conduct. The design-build firm for the project is Capstone Development
of Mobile, Alabama, an organization, which has successfully built similar projects
in a number of other states. The complex is scheduled for completion by August
2001.
- Construction is underway for the development of a Community Center facility
at the School of Social Work on the West Hartford campus. This project is funded
through the generosity of Henry and Judith Zachs, a UConn alumna. The relocated
computer center will go into new facilities on the West Hartford campus. The contractor
for the project is Enfield Builders. The project is scheduled for completion in
July 2001.
- Construction is underway on the new School of Business. The contractor for the
project is FIP Construction of Cheshire. The project's funding will be augmented
with $4.5 million to be raised from private donations. However, these funds will
not be in hand in time to meet cash flow needs, so $3 million in additional funds
were provided for the project from adjustments in the FY 2001 Capital Budget. The
project will be completed in Summer 2001.
- Turner Construction of Milford has signed the construction manager's contract
to complete the construction of the Biological Sciences project. After repeated
discussions, notifications and warnings, the original contractor for the Biological
Sciences project was terminated by the University on February 4, 2000. Grounds
for this termination included:
- Unqualified general contractor staffing
- Removal of key personnel
- Unauthorized substitutions
- Subcontractor mismanagement
- Schedule-failure to comply with contract requirements
- Failure to prosecute the work
- Subcontractor payment irregularities
- Inadequate staffing/manning
- Change order processing failures
- Disregard for University property
- Refusal/delay in allowing document review
- Failure to timely provide general conditions documents
- Inadequate quality control
- Inadequate safety supervision
- The University is working with Liberty Mutual, the Surety that holds the payment
and performance bond to complete the project. On April 10, 2000, Liberty Mutual
informed the University that it is committed to discharging its performance bond
obligations in connection with the project. The start of construction will begin
in June 2001.
- Construction has been completed on a utility tunnel that will connect central
campus buildings to the central utility plant. Inside the tunnel will be the following
services: Steam, Sprinkler Main, Emergency Power, Chilled Water, Domestic Water,
and Tele-Data Systems. The contractor for the project was Allstate Boilers of Farmington.
- All Phase Enterprises of Stafford Springs is the design-build firm for the construction
of the Agricultural Arena. This facility will contain a polo arena to replace the
current outdoor facility. The majority of funds for this project are coming from
private donations. Construction of this project is scheduled to be complete in
July 2001.
- PDS Construction of Bloomfield is the contractor for the construction of the
Precision Manufacturing Facility. The majority of the funding for this project
is a $2 million grant from the federal Economic Development Agency. The project
will be complete in September 2001.
Public Act 99-241 called for, among other things, information on the use of
Connecticut-owned businesses, including businesses owned by women and minorities
on UCONN 2000 program projects. From FY 1996 to FY 2001, construction and related
contracts for the UCONN 2000 program totaled $556.7 million. Twenty-four percent
of this total, or $131.6 million, has gone to set-aside general contractors, contracted
architects and engineers, and subcontractors. Over this period, Connecticut businesses
have accounted for $441.7 million or 79% of the total contracted dollars. Small
business participation has amounted to $66.1 million and minority- and women-owned
participation has accounted for $65.5 million.
- Phase I Debt Service Commitment Bond Issues Completed
Section 10a-109 of the Connecticut General Statutes empowers the University
to issue General Obligation Bonds secured by the State's Debt Service Commitment
(sometimes referred to as "Debt Service Commitment Bonds" or "DSC
Bonds"). These Bonds are issued pursuant to the General Obligation Master
Indenture of Trust, dated as of November 1, 1995, between the University of Connecticut,
as Issuer, and, Fleet National Bank of Connecticut, as Trustee (now State Street
Bank & Trust). The Master Indenture of Trust was approved by the University's
Board of Trustees on November 10, 1995 and the State Bond Commission on December
21, 1995. The University's Board of Trustees and the Governor approve the subsequent
Supplemental Indentures for each bond issue. The State Treasurer and the University
manage the Debt Service Commitment Bond sale process. University General Obligation
Debt Service Commitment Bond Issues are summarized below:
-
| Date of Issue |
Par Amount |
General Obligation Issue |
| Phase I |
|
|
| February 21, 1996 |
$83,929,714.85 |
1996 Series A |
| April 24, 1997 |
24,392,431.65 |
1997 Series A |
| June 24, 1998 |
99,520,000.00 |
1998 Series A |
| April 8, 1999 |
79,735,000.00 |
1999 Series A |
| |
|
|
| Phase II |
|
|
| March 29,2000 |
$130,850,000.00 |
2000 Series A |
| April 11, 2001 |
100,000,000.00 |
2001 Series A |
- The six series of DSC bonds issued totaled $618,427.146.50 in face value, of
which $612,000,000 was for UCONN 2000 projects. The balance, together with accrued
interest and original issue premium, funded the cost of issuance through the Office
of the Treasurer.
- During the process of issuance for the UCONN General Obligation Debt Service
Commitment 2001-A Bond Issue, the University working with the State Treasurer's
Office, was able to achieve an upgrade to "Aa2" from "Aa3" for
the State's Debt Service Commitment Bonds. This is the second rating grade increase
for the DSC bonds by Moody's Investors Service during the past twelve months. The
2001 Series A bonds were sold without any bond insurance, another successful first
time accomplishment for the UCONN 2000 Program. The capital markets thus recognized
the tangible benefits to the State's economy of meeting the infrastructure and
educational goals of the program, as well as the University's success in implementing
them. As of April 2001, the UCONN 2000 Debt Service Commitment bonds were rated "AA" by
Standard & Poor's; "Aa2" by Moody's Investors Service; and "AA-" by
Fitch Investors Service. Also, certain maturities of prior bond issues are secured
by "AAA" rated municipal bond insurance.
- Trustee-Held Construction Fund
Prior to June 1998, all Debt Service Commitment Bond proceeds were deposited
with the Office of the State Treasurer and treated like State bond proceeds. Subsequently,
the Office of the Attorney General determined that UCONN 2000 bonds are issued
by the University, not the State. Accordingly, upon advice of bond counsel and
to conform to the Master Indenture of Trust, Debt Service Commitment Bond construction
fund proceeds were deposited to the Trustee Bank. Bond proceeds for cost of issuance
are still deposited with and disbursed by the Office of the State Treasurer. The
University has directed the Trustee Bank to invest Debt Service Commitment construction
fund proceeds in the State Treasurer's Short Term Investment Fund, that is "AAA" rated
and offers daily liquidity and historically attractive risk-adjusted yields.
- The Indenture of Trust provides that the University is authorized and directed
to order each disbursement from the Construction Account held by the Trustee upon
a certification filed with the Treasurer and Trustee. The Indenture provides that
such certification shall be signed by an Authorized Officer of the University and
include certain disbursement information. Once the Authorized Officer certification
filings are made, the University can directly disburse payments.
- University Special Obligation Revenue Bonds Secured by Pledged Revenues
UCONN 2000 also authorizes the University to issue Special Obligation Revenue
bonds. Unlike Debt Service Commitment Bonds, paid for out of the State's General
Fund, Special Obligation Bonds are paid for out of pledged revenues of the University
as defined in the particular bond series indenture.
- A Special Capital Reserve Fund may be established for University Special Obligation
bond issues only if the University's Board of Trustees determines that the Special
Obligation bond issue is self-sufficient as defined in the Act. The self-sufficiency
finding by the University must be submitted to and confirmed as not unreasonable
or arbitrary by the State Treasurer prior to issuance of the bonds. Once approved,
the Special Capital Reserve Fund is funded at issuance by the University to meet
the minimum capital reserve requirement. However, subject to notification by the
University on or before December 1, annually, if this amount falls below the required
minimum capital reserve, there is deemed to be appropriated from the state General
Fund the sums necessary to restore each such Special Capital Reserve Fund to the
required minimum capital reserve.
- Student Fee Revenue Bonds were issued pursuant to the Special Obligation Indenture
of Trust, dated as of January 1, 1997, between the University, as Issuer, and,
State Street Bank & Trust, as Trustee. This was approved by the University's
Board of Trustees on November 8, 1996. The Supplemental Indenture authorized the
issuance of bonds up to a principal amount not exceeding $30,000,000 for construction
of the South Campus Residence and Dining Hall plus the amounts necessary to fund
a Special Capital Reserve Fund ("SCRF") and to provide for costs of issuance.
- On February 4, 1998, the University issued $33,560,000 of University of Connecticut
Student Fee Revenue Bonds 1998 Series A ("SFR 1998-A Bonds"). The bonds
have a final maturity of November 15, 2027. The University managed issuance and
sale of these bonds and realized a favorable true interest cost over the term.
Debt service for Student Fee Revenue Bond 1998 Series A is paid from revenues from
the student Infrastructure Maintenance Fee instituted in 1997 to provide for such
debt service and help support future operation and maintenance costs for facilities
built or expanded by virtue of UCONN 2000. The University invested the bond proceeds
in the State Treasurer's Short Term Investment Fund, and, in regard to the Special
Capital Reserve Fund, in "AAA" rated fixed income Investment Obligations
as defined in the Special Obligation Indenture of Trust. The State SCRF enhancement
allowed the bonds to obtain a "AA" rating from Standard & Poor's,
a "AA-" from Fitch Investors Service, and an "A-1" from Moody's
Investors Service. The bonds were subsequently covered by municipal bond insurance
and upgraded to a "AAA" at Fitch and Standard & Poor's and "Aaa" at
Moody's Investors Service. In October 1998, Standard & Poor's upgraded the
SFR 1998-A Bond ratings to "AA" with a stable outlook, and in February
2001, Moody's Investors Service upgraded the 1998 bonds to "Aa3".
- On June 1, 2000, the University issued $89,570,000 of the University of Connecticut
Student Fee Revenue Bonds 2000 Series A pursuant to the Special Obligation Master
Indenture and the Special Obligation Student Fee Revenue Bonds Second Supplemental
Indenture, dated as of May 1, 2000. The Indenture authorized issuance of bonds
up to a principal amount not exceeding $90,000,000 for construction of the Hilltop
Dormitory; Hilltop Student Rental Apartments; and the Parking Garage South Projects
and provide for capitalized interest and costs of issuance. The Special Obligation
Student Fee Revenue Bonds 2000 Series A do not have a Special Capital Reserve Fund
("SCRF"). The University managed issuance and sale of these bonds and
realized a favorable true interest cost. The bonds have a final maturity of November
15, 2029. Debt service is paid from Pledged Revenues as defined pursuant to the
Indentures. Bond proceeds are being used to provide the aforementioned student
housing and parking garage. The University has invested the bond proceeds in the
State Treasurer's Short Term Investment Fund.
- The University obtained a "AA-" stand-alone credit rating from Standard & Poor's
for its second issue of Special Obligation Bonds, showing its ability to professionally
administer complexities of the tax-exempt bond program. This was the first time
the University obtained a credit rating based on its own merit without use of Debt
Service Commitment or Special Capital Reserve Fund state-backed credit supports.
This signaled a vote of confidence by capital markets in the University and its
ability to provide benefits to the State's economy. Also, Special Obligation Student
Fee Revenue Bonds 2000 Series A bonds were rated "A-1" by Moody's on
a stand-alone basis. At issuance, certain maturities of the bonds were covered
by municipal bond insurance and upgraded to a "AAA" rating at Fitch and
Standard & Poor's, and "Aaa" at Moody's.
- Future Bond Issues
The University currently anticipates offering a new Debt Service Commitment
Bond issue for all or part of the sixth year $100 million authorization during
the Spring of 2002. Generally, the University plans on issuing a series of new
Debt Service Commitment bonds at least every twelve months. Also, the University
could issue Special Obligation Revenue bonds for certain projects with capacity
for financial self-sufficiency, and/or if aggregate pledged revenues are sufficient
to meet requirements of the Special Obligation Indenture. Depending on market
conditions and other factors, the University also might issue refunding bonds
at some future date.
The UCONN 2000 endowment matching gift program continues to be a powerful incentive
for donors. As of March 31, 2001, total match-eligible calendar year gift receipts
are $2,319,229, a 26 percent increase over the same period last year.
At June 30, 2000, annual private donations reached another all-time high of
$37 million. The Foundation realized a total return on investment of 16.5 percent,
widely outperforming our composite benchmark index of 9.1 percent. A combination
of new contributions maximized by the state matching program and strong investment
performance made UConn's endowment one of the fastest growing nationally.
'The $20 million in 1:1 state match funds for private gifts, as provided by
the original UCONN 2000 legislation, is in-hand. During the first year of the program,
$9.1 million in match-eligible gifts was received; an additional $6.5 million was
received in calendar year 1997; $4.4 million was received in calendar year 1998.
'In recognition of the program's success, the General Assembly enacted a continuation
and restructuring of the match on a 1:2 basis (one state dollar to every two private
dollars). The State of Connecticut's grant will total up to $52.5 million from
fiscal year 2000 to fiscal year 2007, depending on the level of match-eligible
donations actually received on behalf of the University by December 31, 2005. Total
match-eligible receipts for calendar year 2000 was $16.9 million. This resulted
in an over subscription of $1.9 million, which will be submitted for calendar year
2001 and is expected to be received in the fall.
Significant Commitments
In December 2000, James L. and the late Shirley A. Draper, both Class of 1941,
donated $1 million to endow the James L. and Shirley A. Draper Chair in American
History. A prominent scholar will be named to the new chair by the 2002-03 academic
year. The Drapers had provided previously for the University in their estate plans
to establish scholarships to UConn for students from Litchfield County.
Dr. Raymond R. and Beverly Sackler donated $200,000 to the School of Fine Arts
to support the Raymond and Beverly Sackler Composition Award. It provides the opportunity
to invite aspiring, young composers to create new works that will be premiered
and performed at the University of Connecticut.
Keith Fox, Class of 1980, donated $1 million to establish the Auran J. Fox Chair
in e-Business within the School of Business at the Storrs Campus.
In February 2001, the Kluge Foundation donated $500,000 in support of the Thomas
J. Dodd Research Center. The funds will support the Dodd Human Rights Prize, which
will honor an individual who has made a significant contribution in the area of
human rights internationally.
|